Project overview
- Project status: Completed
- Start on Site: November 2008
- Construction Team: Balfour Beatty
- Architects: Aedas
- Completion: June 2010
Castlefield High School has benefited from a £4million investment which has seen the construction of a brand new school that was completed in June 2010.
The new build comprises state-of-the-art facilities to help young people overcome their individual difficulties and reach their full emotional, social and educational potential.
The project was completed in two phases;
Phase 1: Construction of the new 55 place educational, behavioural and social difficulties (EBSD) High School built on the same site.
Phase 2: This commenced with the former Primary School building being demolished, followed by extensive soft and hard landscaping to the front of the building, including the construction of a new multi use games area pitch-space which can be used for 5 a side or basketball.
The Castlefield Campus has facilities for joint provision training, multi-agency, meetings, parent/carers meeting room, extended school provision and community use.
For more information please see Castlefield Campus Website.