Brunswick Private Finance Initiative (PFI)
The timetable
The huge improvements the PFI will bring can't happen overnight. We must get it exactly right so that local people get what they want and need.
Here are the next steps . . .
Autumn 2011
-
We send a detailed report to the government that shows how we'll meet the aims of the project, and outlines the legal and financial arrangements.
Winter 2011
-
Government approves this report
-
Potential partners (Fern Consortium and Solutions 4 Brunswick) submit their final regeneration proposals
-
Open days where you can see and comment on these proposals.
Spring 2012
-
We assess the final regeneration proposals and send a second detailed report to the government
-
The government approves the second report
-
We select Fern or Solutions 4 Brunswick as the final PFI partner
-
The chosen PFI partner applies for planning permission.
Summer 2012
-
Planning decisions received
-
PFI contract finalised
-
Consultation with people affected by demolition.
-
Government approves final report
Autumn 2012
-
Improvements start!