June 2024
Good progress has been made with a number of the planned Phase 2 improvements listed below.
Burnage Lane/Grangethorpe Drive Junction, Chapel Street, Broom Lane Crayfield Road and Marley Road
All major works have been completed with new kerbs, tactile paving and surfacing.
Below shows completed works on Burnage Lane rain garden, Burnage Lane green area, and Alexander Drive / Burnage Lane Junction:
Below shows completed work on Chapel Street:
Below shows completed work on Marley Road and Crayfield Road:
Below shows the new signal-controlled crossing on Broom Lane:
Cromwell Grove
Proposals at Cromwell Grove were revised due to the height of the road being almost level with the pavement. It was not possible to raise the road level any higher at these junctions. Crossing points for pedestrians have still been provided across the junction as originally proposed, and the existing traffic calming measures have been retained along with the 20mph speed limit. Download the updated plan.
The works are expected to complete early July 2024.
Broom Lane
Further updates will be provided in due course.
Matthews Lane, Slade Lane/Moseley Road and A6 Arcadia Crossing
We are currently in the process of appointing a contractor aiming to commence works in summer 2024. Residents and businesses will receive a letter about the detail of these planned works and updates will be shared here.