Traffic management and working patterns
The effort to make the Ancoats measures permanent will follow this plan. But, these dates might change due to weather and material availability.
Radium Street
- Removal of existing kerbs and installation of new kerbs – 28 to 29 July
- Footway resurfacing – 30 July
- Installation of signs and lining – 31 July
- Installation of planter – 1 August
Sherratt Street
- Removal of existing kerbs drainage, and installation of new kerbs and drainage – 30 to 31 July
- Footway resurfacing – 1 August
- Installation of signs and lining – 4 August
- Installation of planter – 5 August
Henry Street
- Excavation and installation of two islands – 4 to 5 August
- Island resurfacing – 6 August
- Installation of signs and lining – 7 August
- Installation of planter – 8 August
Gunn Street
- Removal of existing kerbs drainage, and installation of new kerbs and drainage – 11 to 18 August
- Flag footway – 19 to 26 August
- Installation of signs and lining – 27 to 28 August
- Installation of planter – 29 August