Traffic management and working patterns

The effort to make the Ancoats measures permanent will follow this plan. But, these dates might change due to weather and material availability.

Radium Street

  • Removal of existing kerbs and installation of new kerbs – 28 to 29 July
  • Footway resurfacing – 30 July
  • Installation of signs and lining – 31 July
  • Installation of planter – 1 August

Sherratt Street

  • Removal of existing kerbs drainage, and installation of new kerbs and drainage – 30 to 31 July
  • Footway resurfacing – 1 August
  • Installation of signs and lining – 4 August
  • Installation of planter – 5 August

Henry Street

  • Excavation and installation of two islands – 4 to 5 August
  • Island resurfacing – 6 August
  • Installation of signs and lining – 7 August
  • Installation of planter – 8 August

Gunn Street

  • Removal of existing kerbs drainage, and installation of new kerbs and drainage – 11 to 18 August
  • Flag footway – 19 to 26 August
  • Installation of signs and lining – 27 to 28 August
  • Installation of planter – 29 August