Birley Fields Campus, George Parr Road

  1. Location

    Birley Fields Campus, George Parr Road

  2. Ward

    Hulme

  3. Contractor

    Kier Construction

  4. Dates and Times

    • 11 July
    • 18 July
    • 25 July
    • 1 August
    • 8 August
    •  

  5. Reason

    Erection of a scaffold adjacent to the public footpath. Highways lane closure in place which is only possible at the weekend in order for work to be carried out safely.

  6. Schedule of Works

    • Erecting scaffold only between 8.30am to 2pm using hand tools and materials hoist.
    • No deliveries all materials are on site already.
    • No works on site until 8.30am.
    • Staff will park away from site.
    • Staff will be briefed on noise prior to commencing works. No radio policy on site.
    •  