Location
Birley Fields Campus, George Parr Road
-
Ward
Hulme
-
Contractor
Kier Construction
-
Dates and Times
- 11 July
- 18 July
- 25 July
- 1 August
- 8 August
-
Reason
Erection of a scaffold adjacent to the public footpath. Highways lane closure in place which is only possible at the weekend in order for work to be carried out safely.
-
Schedule of Works
- Erecting scaffold only between 8.30am to 2pm using hand tools and materials hoist.
- No deliveries all materials are on site already.
- No works on site until 8.30am.
- Staff will park away from site.
- Staff will be briefed on noise prior to commencing works. No radio policy on site.