Princess Street Pedestrian Improvements
You Said, We Did
At the end of 2025 and the start of 2026, we asked people what they thought about plans to improve Princess Street and make it safer, easier and more pleasant for people walking, wheeling and cycling.
People shared their views through an online survey, city centre drop-in events, an online meeting, and conversations at bus stops along the route.
Nearly 150 people took part and told us what they thought about proposals including:
- Wider pavements
- Better pedestrian crossings at Mosley Street and Portland Street
- Raised crossings on side streets to slow turning vehicles
- Improved paving
- Less street clutter
- Changes to parking and loading areas
- Clearer cycle lane markings
- Moving some bus stops
What you told us
The feedback showed strong support for the improvements.
Nearly three-quarters (73%) of respondents agreed that the changes would make Princess Street a safer and more attractive place to walk, wheel or cycle. Only 15% disagreed.
The most popular proposals were:
- Wider pavements
- Safer and easier pedestrian crossings
- Removing obstacles and clutter from footways
- Better facilities for people walking and using public transport
Many people said the changes would help tackle overcrowding on pavements and make it easier to move around busy bus stops.
What we changed
Some residents and businesses on Princess Street raised concerns about parts of the scheme.
After meeting with them and carrying out a site visit, we made several changes to the plans, including:
- Adding a new loading bay for businesses
- Moving a bus stop to a more suitable location
You can download the finalised plans for Princess Street which show the following changes:
- Wider pedestrian crossings at the junction with Mosley Street and the junction with Portland Street
- Wider footways on the south side of Princess Street
- Double yellow lines and kerb blips show where there is no parking and loading allowed
- Side road treatments at the entrance to Back George Street, George Street (north and south sides), St James Street (north side), Faulkner Street (north side), Reyner Street
- Existing No Motorised vehicles at entrance off Portland St and Bus Gate to be retained
- Removal of pay and display bays to be replaced with a new bus stop between George Street and St James Street, a loading bay on George Street (south), and a loading bay on Faulkner Street (north)
- Improved bus stops on Princess Street, between George Street and St James Street (south side), and between St James Street and Faulkner Street (north side)
- Cycle Awareness symbols and cycle lane to advanced stop line for cyclists
What happens next?
The Traffic Regulation Orders for the project have now been advertised, and the tender process is underway.
Construction is expected to start in early 2027.